Change Requests

Form Reference Guide

version
2026 R2

Form ID: (PM308500)

Attention: This form is available only if the Change Requests feature is enabled on the Enable/Disable Features (CS100000) form.

You can use this form to view, modify, add, or delete a change request.

Form Toolbar

The form toolbar and More menu include the buttons and commands described below.

Command Description
Approve

Approves the change request and changes its status from Pending Approval to Open.

When you click this command, the Enter Reason dialog box opens if Is Optional or Is Required is selected in the Reason for Approval box on the Rule Actions tab of the Approval Maps (EP205015) form for the map. In the dialog box, you can (if Is Optional is selected) or must (if Is Required is selected) enter the reason the document is being approved.

This command is available if the selected change request has the Pending Approval status.

For more information, see Approval Configuration: Approval Maps.

Cancel Cancels the change request, which changes its status to Canceled. A change request with this status cannot be edited. To edit it, you need to first manually change its status to On Hold (by clicking the Hold button).

This command is available if the change request has the On Hold, Pending Approval, Open, or Rejected status and is not linked to a change order.

Close Closes the change request, which changes its status to Closed.

This command appears if the change request has the Open status and is linked to a cost change order that has the Closed status.

A cost change order is a change order contains the cost part of the change request and, optionally, the commitment part. That is, the cost change order belongs to a change order class with the Cost Budget check box selected and the Revenue Budget check box cleared on the Change Order Classes (PM203000) form.

Create Change Order

Creates a change order based on the change request.

This command appears if the change request has the Open status.

If Copy Settings on Budget Line Creation From is set to Source Document on the Projects Preferences (PM101000) form, the Description, UOM and Unit Rate of new revenue and cost budget lines of the change order are populated from the corresponding change request lines.

Email Sends the currently selected change request as an email.
Hold

Changes the status of the record to On Hold. You click this command when you want to make changes to the record or pause its processing.

This command appears if the change request has the Rejected, Open, or Pending Approval status.

Link Project Files

Opens the Link Project Files dialog box, where you can select project files and link them to the change request by clicking Add Link. You can also select another project and link its files to the change request.

This command appears only if the Document Management feature is enabled on the Enable/Disable Features (CS100000) form.

Print Opens the report that is specified for the CHANGE REQUEST mailing of the corresponding project on the Mailing & Printing tab of the Projects (PM301000) form, to give you a print-friendly version of the change request. If the corresponding project has no mailing with the CHANGE REQUEST identifier, an error occurs.
Reassign

Opens the Reassign Approval dialog box, in which you can specify a new approver for the change request the reassignment of approvals is allowed in the related rule of the approval map on the Approval Maps (EP205015) form.

This command is available if the change request has the Pending Approval status.

For more information, see Approval Configuration: Approval Maps.

Recalculate External Tax

Recalculates all taxes in the change request through the configured external tax provider.

This command is available if the change request has the On Hold or Open status.

The command appears if the External Tax Calculation Integration feature is enabled on the Enable/Disable Features (CS100000) form.

Reject

Rejects the change request and changes its status from Pending Approval to Rejected.

When you click this command, the Enter Reason dialog box opens if on the Rule Actions tab of the Approval Maps (EP205015) form for the applicable map, Is Optional or Is Required is selected as the reason for rejection. In the dialog box, you can (if Is Optional is selected) or must (if Is Required is selected) enter the reason the document is being rejected.

This command is available if the change request has the Pending Approval status.

For more information, see Approval Configuration: Approval Maps.

Remove Hold

Changes the status of the change request to Open, or to Pending Approval if an approval map is specified for change requests on the Projects Preferences (PM101000) form.

This command appears if the change request has the On Hold status.

Validate Address

Validates the address on the Address tab by using integration with a specialized address validation third-party service.

This command is available if the Override Address check box is selected or the Validated check box is cleared.

The command appears if the Address Validation Integration feature is enabled on the Enable/Disable Features (CS100000) form.

Table 1. Enter Reason Dialog Box. You use this dialog box to enter the reason you are approving or rejecting the selected document. The dialog box is opened when you click one of the following on the form toolbar of the current form:
  • Approve if Is Optional or Is Required is selected for the map in the Reason for Approval box of the Rule Actions tab of the Approval Maps (EP205015) form
  • Reject if Is Optional or Is Required is selected for the map in the Reason for Rejection box of the Rule Actions tab of the Approval Maps (EP205015) form
Element Description
Unnamed text box The reason the document is being approved or rejected.
This dialog box has the following buttons.
OK Saves the specified reason and closes the dialog box.
Cancel Closes the dialog box without saving the specified reason.

Reassign Approval Dialog Box

In this dialog box, you can specify the new approver to whom you want to reassign the selected record or records. The dialog box opens when you click Reassign.

Element Description
New Approver The name of the employee to whom you want to reassign the selected record or records.
Ignore Approver's Delegations

A check box that indicates (if selected) that the system will assign the selected records to the specified new approver but not to their delegate, even if the new approver is unavailable and has a delegate specified for the current business date.

If the check box is cleared and if the new approver is not available and has a delegate specified for the current date, the system will reassign the selected records to the delegate if they’re available. If the delegate is unavailable, the system will reassign the requests to the delegate of the delegate. The system will continue the search in this way until:

  • It assigns an approver with no active delegations set up for the current date.
  • It detects a loop in the chain of delegations. In this case, the system will prompt you to specify a different approver.
This dialog box has the following buttons.
Reassign Closes the dialog box and reassigns the selected record or records to the specified new approver if the reassignment of approvals is allowed in the related rule of the approval map on the Approval Maps (EP205015) form.
Cancel Closes the dialog box and cancels the reassignment of the selected record or records to the new approver.

Summary Area

In this area, you can specify or view the basic settings of a change request.

Element Description
Reference Nbr. The reference number of the change request, which the system automatically assigns by using the numbering sequence specified on the Projects Preferences (PM101000) form.
Status

The status of the change request, which can be one of the following:

  • On Hold: The user can edit or delete the change request with this status but cannot link the change request to a change order or create a change order based on the change request. The amounts and quantities in this change request are not included in the potential amounts and quantities of the project budget.
  • Pending Approval: The change request has been taken off hold (that is, Remove Hold was clicked) and is awaiting approval. The amounts and quantities in this change request are not included in the potential amounts and quantities of the project budget.

    This status is available if the approval map has been specified in the Change Request Approval Map box on the Projects Preferences (PM101000) form.

    Tip: On the Approvals (EP503010) form, a change request with this status is visible to the employee who has been assigned to approve the change request.
  • Rejected: The employee who was assigned to approve the change request has rejected it. The change request can be put on hold for further editing. The amounts and quantities in this change request are not included in the potential amounts and quantities of the project budget.

    This status is available if the approval map has been specified in the Change Request Approval Map box on the Projects Preferences (PM101000) form.

  • Open: The employee who was assigned to approve the change request has approved it. If no approval is configured for change requests, the system assigns this status to the change request immediately after a user clicks Remove Hold on the form toolbar. The user can create a change order for the change request, link the change request to a change order, or assign it the On Hold status for further editing. The amounts and quantities in this change request are included in the potential amounts and quantities of the project budget.
  • Canceled: The change request has been canceled. The change request cannot be edited and change orders cannot be based on it. The amounts and quantities in this change request are not included in the potential amounts and quantities of the project budget.
  • Closed: The change request has been processed in full; it cannot be edited. The amounts and quantities in this change request are not included in the potential amounts and quantities of the project budget.
Change Date

The date on which the changes made with the change request should be recorded in the project balances.

The change date must belong to an open financial period of the master calendar.

Contract Change (Days) A positive or negative number of days that represents the delay of the contract.
External Ref. Nbr. The external reference number. You manually enter this number, which can be an identifier required by the customer or a number from an external system integrated with Acumatica ERP.
Description The description of the change request.
Project

The project associated with the change request.

If the change request has at least one line on the Estimation tab, you cannot change the project.

Customer The customer associated with the project.
Change Request Nbr.

The unique number that identifies this change request’s place among change requests within the project. The system assigns this number sequentially, starting from 0001. Duplicate numbers within the project are not allowed.

Before a project is selected in the Project box, this box is read-only and contains N/A.

You can edit this number only if the change request has the On Hold status.

Common Task for Change Request

The common task that the system uses as a template for creating a project task for the change request.

By default, the system inserts the common task selected in the Common Task for Change Request box on the General tab of the Projects Preferences (PM101000) form.

You can select another common task or clear the box. If the box is empty, the system uses the project's default task settings for the change request's tasks.

You can change the specified number if the change request has the On Hold status.

The box becomes read-only after the system creates a corresponding project task.

Change Request Task Nbr.

The unique identifier of the project task that the system will create for the selected change request. The structure of the identifier is defined by the PROTASK segmented key on the Segmented Keys (CS202000) form. Duplicate numbers of change request tasks within the project are not allowed.

You can change this number if the change request has the On Hold status.

The box becomes read-only after the system creates the project task.

You can select this project task in the change request lines before the change request is saved. When you save it, the system creates a new project task with this number, based on the specified common task.

Change Order Nbr.

The reference number of the revenue change order that is linked to the change request.

A revenue change order is a change order that belongs to a change order class that has the Revenue Budget check box selected on the Change Order Classes (PM203000) form.

Cost Change Order Nbr.

The reference number of the cost change order that is linked to the change request. This box is shown only if the change request is linked to the cost change order.

A cost change order is a change order contains the cost part of the change request and, optionally, the commitment part. That is, the cost change order belongs to a change order class with the Cost Budget check box selected and the Revenue Budget check box cleared on the Change Order Classes (PM203000) form.

Unit Price Source

The source that determines the unit price of estimation lines in the change request, which can be either of the following:

  • Unit Cost and Markups: The unit price is calculated based on the unit cost and price markup as follows:
    Unit Price = Unit Cost + (Unit Cost × Price Markup (%) / 100)
  • Sales Prices: The unit price is copied from the sales price of the selected inventory item. The system:
    1. Searches for the sales price on the Sales Prices (AR202000) form. The price must be effective on the date specified in the Change Date box of the current form.
    2. If no applicable sales price is found, uses the default price specified in the Default Price box on the Price/Cost tab of the Stock Items (IN202500) or Non-Stock Items (IN202000) form.
    Tip: For more details on how the price is selected, see Sales Prices: Rules of Price Selection.

When you create a change request, the system inserts the unit price source specified for the selected project. You can change the option if the change request has the On Hold status.

If Sales Prices is selected:

  • The Markup Total box is hidden and excluded from the Price Total calculation.
  • The Price Markup (%) and Line Markup (%) columns are hidden.
  • The Line Amount is equal to the Ext. Price.
  • The Markups tab is hidden and its existing markup lines are cleared.
  • On the Taxes tab, the taxable amount is calculated only from estimation lines.

If you change the selected option after estimation lines have been added, the system updates the unit prices of the existing estimation lines according to the newly selected source.

Cost Total The total of the Ext. Cost column on the Estimation tab.
Line Total The total of the Line Amount column on the Estimation tab.
Markup Total The total of the Markup Amount column on the Markups tab.
Gross Margin (%) The gross margin percentage. The system calculates this percentage by using the following formula: Gross Margin (%) = (Price Total – Cost Total) / Price Total * 100.
Price Total The sum of the Line Total and Markup Total.
Tax Total

The total tax amount of the change request. The system calculates this amount as the sum of the Tax Amount values on the Taxes tab.

For built-in tax calculation, this amount is updated when you do any of the following:

  • Modify the Change Date
  • Add, modify, or delete an estimation or markup line
  • Change an amount or tax category in an estimation or markup line
  • Change the tax zone, tax calculation mode, or tax lines on the Taxes tab

For external tax calculation, this amount is updated when you save the change request, remove it from hold, create a change order for this change request or recalculate external taxes.

Change Total

The total amount of the change request, including taxes. The system calculates this amount as follows:

  • If only exclusive taxes apply or the Net option is selected in the Tax Calculation Mode box: Price Total + Tax Total
  • If only inclusive taxes apply or the Gross option is selected in the Tax Calculation Mode box: Price Total
  • If both inclusive and exclusive taxes apply: Price Total plus the exclusive tax amounts

For built-in tax calculation, this amount is updated when you do any of the following:

  • Modify the Change Date.
  • Add, modify, or delete an estimation or markup line.
  • Change an amount or tax category in an estimation or markup line.
  • Change the tax zone, tax calculation mode, or tax lines on the Taxes tab.

For external tax calculation, this amount is updated when you save the change request, remove it from hold, create a change order for this change request or recalculate external taxes.

Estimation Tab

This tab lists all the changes that may affect the project budget.

Table 2. Table Toolbar.

The table toolbar includes the buttons described below.

Button Description
Add Commitments

Opens the Add Commitments dialog box, in which you can select one or multiple lines of existing purchase orders associated with the project and add them as estimation lines.

If the Construction feature is enabled on the Enable/Disable Features (CS100000) form, you can also select lines of existing subcontracts.

Table 3. Table Columns
Column Description
Project Task

The project task that is associated with the cost part of the estimation line.

If you add a new line and the project has the default project task, this task is automatically populated in the column.

Account Group

The expense account group that is associated with the cost part of the estimation line.

You can select an account group of the Expense type, or an account group of the Off-Balance type for which the Expense check box is selected on the Account Groups (PM201000) form.

If more than one account group of the Expense type is configured and you track the cost budget at the item level, you can use a project task or an item as the source of the account group. When you add the line, the system inserts an account group based on the first applicable source:

  • If you select a project task first and its default expense account has an account group, this account group is inserted.
  • If you select an item first and its COGS account has an account group, this account group is inserted.
Attention: The system inserts the default account group only when this column is empty. You can override the default settings.

For an inventory item selected in the line, the system automatically inserts the account group as follows:

  • If the line contains a non-stock item, the system inserts the account group mapped to the account specified in the Expense Account box on the GL Accounts tab of the Non-Stock Items (IN202000) form.
  • If the line contains a stock item, the system inserts the account group mapped to the account specified in the COGS Account box on the GL Accounts tab of the Stock Items (IN202500) form.

If you add the line and select a project task, the system inserts the account group of the default expense account of the project task.

Cost Code

The cost code associated with the cost part of the estimation line.

This column is shown if the Cost Codes feature is enabled on the Enable/Disable Features (CS100000) form.

Inventory ID

The identifier of the stock or non-stock item associated with the cost part of the estimation line.

If you specify no inventory item, for the change order line created based on this estimation line, the system uses the empty item code, which is specified on the Projects Preferences (PM101000) form).

Description The description of the estimation line.
Quantity The quantity of the estimation line.
UOM

The unit of measure associated with the cost part of the estimation line. If an inventory item is selected in the Inventory ID column, the system automatically inserts the base unit of measure of this inventory item. You can change it to another UOM available for the item.

If the Copy Settings on Budget Line Creation From box on the Projects Preferences (PM101000) form is set to Source Document, the system copies this UOM to a new project budget line if the applicable budget level is set to Task or Task and Cost Code.

If the budget level is set to Task and Item or Task, Item, and Cost Code, the system uses the base UOM of the inventory item instead. The same UOM population rules apply when change request lines are added to a change order.

If the UOM of this line cannot be converted to the UOM of another line with the same budget key, the system displays a warning, but you can save a change request.

Unit Cost

The cost of the estimation line.

By default, the system populates this column with the cost of the inventory item selected in the budget line. For more details on how the system selects the cost, see Project Budget: Unit Rate in Budget Lines.

If the Multicurrency Projects feature is enabled on the Enable/Disable Features (CS100000) form, the system converts the retrieved unit cost to the project currency by using the exchange rate of the project.

You can enter the cost manually or change the default cost.

Ext. Cost

The extended cost of the estimation line, which the system calculates by multiplying the Quantity and Unit Cost values of the line.

Price Markup (%)

The markup percentage that the system uses to calculate the Unit Price based on the Ext. Cost.

By default, the system retrieves the following markup depending on the type of the revenue inventory item:

  • For a stock item: The Markup % of the item from the Price/Cost tab of the Stock Items (IN202500) form
  • For a non-stock item: The Markup % of the item from the Price/Cost tab of the Non-Stock Items (IN202000) form

If the default item markup is 0, the system populates the markup with the Default Price Markup (%) specified on the General tab of the Projects Preferences (PM101000) form.

Revenue Task

The project task that is associated with the revenue part of the estimation line.

If you add a new line and the project has the default project task, this task is automatically populated in the column.

Revenue Account Group

The income account group that is associated with the revenue part of the estimation line.

By default, the system populates the column with the Default Revenue Account Group of the expense account group of the estimation line, which is specified in the Summary area of the Account Groups (PM201000) form. The value can be overridden.

If only one account group of the Income type is configured in the system, the system inserts it by default.

If more than one account group of the Income type is configured and you track the revenue budget at the item level, you can use a project task or an item as the source of the account group. When you add the line, the system inserts the account group based on the first applicable source:

  • If you select a revenue task first and its default sales account has an account group, this account group is inserted.
  • If you select a revenue item first and its sales account has an account group, this account group is inserted.

If you add the line and select a project task, the system inserts account group of the default sales account of the revenue project task.

Attention: The system inserts the default account group only when this column is empty. You can override the default settings.
Revenue Inventory ID

The identifier of the stock or non-stock item associated with the revenue part of the estimation line.

If you specify no inventory item, for the change order line created based on this estimation line, the system uses the empty item code, which is specified in the Empty Item Code box on the Projects Preferences (PM101000) form.

This column is shown if Task and Item is selected as the Revenue Budget Level of the project on the Summary tab of the Projects (PM301000) form.

Revenue Code

The cost code associated with the revenue part of the estimation line.

If you specify no cost code, for the change order line created based on this estimation line, the system uses the default cost code specified on the Cost Codes (PM209500) form.

This column is shown if the Cost Codes feature is enabled on the Enable/Disable Features (CS100000) form and Task and Cost Code is selected as the Revenue Budget Level of the project on the Summary tab of the Projects (PM301000) form.

Unit Price
The price of the estimation line, which the system calculates by using the following formula.
Unit Price = Unit Cost + Unit Cost * Price Markup (%) / 100

If the Multicurrency Projects feature is enabled on the Enable/Disable Features (CS100000) form, the system converts the retrieved unit price to the project currency by using the exchange rate of the project.

You can enter this price manually or change the default price. If you have entered the unit price manually and saved the change request and you change the change request date, this price will not be automatically updated by the system to the correct price for the new change request date.

Ext. Price

The extended price for the estimation line, which the system calculates by multiplying the Quantity and Unit Price values for the line.

If the estimation line has an account group selected in the Revenue Account Group column or a project task selected in the Revenue Task column, the Ext. Price cannot be 0.

Line Markup (%)

The line markup percentage of the estimation line.

By default, the system populates the column with the Default Line Markup (%) of the expense account group of the estimation line, which is specified on the Change Request Settings tab of the Account Groups (PM201000) form.

Line Amount The total amount of the revenue part of the estimation line that the system calculates by using the following formula.
Ext. Price + Ext. Price * Line Markup (%) / 100
Vendor

The vendor associated with the estimation line.

The list of vendors available for selection may be limited based on the role or roles assigned to the user account to which you are signed in if the Customer and Vendor Visibility Restriction feature is enabled on the Enable/Disable Features (CS100000) form. In this case, the Restrict Visibility To box appears on the Financial tab of the Vendors (AP303000) form. With the feature enabled, a vendor is available for selection if one of the following is true:
  • The Restrict Visibility To box is empty for the vendor—that is, the vendor’s visibility is not restricted.
  • A branch, company, or a company group is specified in the Restrict Visibility To box for the vendor, and your user account has the role specified in the Access Role box of the Configuration Settings section of one of the following: the Branch Details tab of the Branches (CS102000) form for the selected branch, or the Company Details tab of the Companies (CS101500) form for the selected company or a company within the company group.
Create Commitment

A check box that indicates (if selected) that the system produces a commitment line based on this estimation line when the change request is linked to a change order.

By default, the system selects this check box if the expense account group of the estimation line has the Create Commitment check box selected on the Change Request Settings tab of the Account Groups (PM201000) form.

Commitment Type

The type of the commitment assigned to the commitment line, which the system generates based on the estimation line when the change request is linked to a change order.

If the Create Commitment check box is selected, you can select one of the following options:

  • Normal Purchase Order (default).
  • Project Drop-Ship.
  • Subcontract: This option is available only if the Construction feature is enabled on the Enable/Disable Features (CS100000) form.
Commitment Nbr.

The reference number of the existing purchase order or subcontract associated with the estimation line. You can select a subcontract or a purchase order of the Normal or Project Drop-Ship type. Documents with the On Hold, Pending Approval, or Rejected status aren't available for selection.

If a vendor is specified in the line, only documents associated with that vendor are available for selection. You can click the selected reference number to open the document on the Purchase Orders (PO301000) or Subcontracts (SC301000) form in a new browser tab.

If you select a commitment number without selecting a commitment line number, New Line is inserted in the Status column. A new line will be added to the selected commitment document when the related change order is released.

The column is available for editing only if the change request has the On Hold status. If the Create Commitment check box is cleared for the line, the column is empty and unavailable for editing.

The column is shown if the Construction feature is enabled on the Enable/Disable Features (CS100000) form.

PO Nbr.

The reference number of the existing purchase order associated with the estimation line. You can select a purchase order of the Normal or Project Drop-Ship type. Documents with the On Hold, Pending Approval, or Rejected status aren't available for selection.

If a vendor is specified in the line, only documents associated with that vendor are available for selection. You can click the selected reference number to open the document on the Purchase Orders (PO301000) or Subcontracts (SC301000) form in a new browser tab.

If you select a commitment number without selecting a commitment line, New Line is inserted in the Status column. A new line will be added to the selected commitment document when the related change order is released.

The column is available for editing only if the change request has the On Hold status. If the Create Commitment check box is cleared for the line, the column is empty and unavailable for editing.

This column appears if the Construction feature is enabled on the Enable/Disable Features (CS100000) form.

Commitment Line Nbr.

The line number of the purchase order or subcontract selected in the Commitment Nbr. column.

When you select a line, the value in the Status column is inserted as follows:

  • Update if the selected line is open. The line will be updated when the related change order is released.
  • Reopen if the selected line is completed or canceled. The line will be reopened when the related change order is released.

For an estimation line with the New Line or New Document status, this column is empty.

The column is available for editing only if the change request has the On Hold status. If the Create Commitment check box is cleared for the line, the column is empty and unavailable for editing.

This column appears if the Construction feature is enabled on the Enable/Disable Features (CS100000) form.

PO Line Nbr.

The line number of the purchase order selected in the PO Nbr. column.

When you select a line, the value in the Status column is inserted as follows:

  • Update if the selected line is open. The line will be updated when the related change order is released.
  • Reopen if the selected line is completed or canceled. The line will be reopened when the related change order is released.

For an estimation line with the New Line or New Document status, this column is empty by default.

The column is available for editing only if the change request has the On Hold status. If the Create Commitment check box is cleared for the line, the column is empty and unavailable for editing.

This column appears if the Construction feature is disabled on the Enable/Disable Features (CS100000) form.

Status

Read-only. The status of the commitment line in the related change order, which indicates the action to be performed when the change order is released. The status can be one of the following options:

  • New Document: A new commitment document will be created.
  • New Line: A new line will be added to the selected commitment document (purchase order, project drop-ship order, or subcontract), which will also be reopened if it is closed.
  • Reopen: The selected completed or canceled commitment line will be updated, and the related document will be reopened if it is closed.
  • Update: The selected open commitment line will be updated.

If the Create Commitment check box is cleared for the line, this column is empty.

Tip: If the New Line or New Document status is assigned to the commitment line, the line’s quantity cannot be negative. To be able to specify a negative amount in the commitment line with any of these statuses, you must set the quantity of the line to 0.
Revenue Tax Category

The tax category applied to the line amount of the revenue portion.

When you add a line, the system inserts the tax category based on the following priority:

  1. The tax category of the stock or non-stock item selected in the Revenue Inventory ID column
  2. The tax category of the selected Revenue Task

If neither the inventory item nor the revenue task has a tax category, this column is empty. You can select a tax category manually.

For built-in tax calculation, taxes are recalculated when you change the tax category. For external tax calculation, the change is applied the next time external taxes are recalculated.

Table 4. Add Commitments Dialog Box.

In this dialog box, which opens when you click Add Commitments on the table toolbar, you can select specific lines or all the lines and add them to the change request.

The table in the dialog box shows the list of purchase order lines associated with the project for which you can process a change order. If the Construction feature is enabled on the Enable/Disable Features (CS100000) form, the table also shows the list of subcontract lines associated with the project.

Element Description
The Selection area of the dialog box has the following elements, which you can use to select the criteria of commitment lines to be displayed in the table.
Vendor The vendor for which you want to view commitment lines. If you want to see the document lines associated with all vendors, leave this box empty.
Cost Code From

The first cost code of the range for which you want to view commitment lines. If you want to see the commitment lines associated with all cost codes, leave this box empty.

This box is shown if the Cost Codes feature is enabled on the Enable/Disable Features (CS100000) form.

Cost Code To

The last cost code of the range for which you want to view commitment lines. If you want to see the commitment lines associated with all cost codes, leave this box empty.

This box is shown if the Cost Codes feature is enabled on the Enable/Disable Features (CS100000) form.

Inventory ID The inventory item for which you want to view commitment lines. If you want to see the commitment lines associated with all items, leave this box empty.
PO Nbr.

The reference number of the purchase order.

Project Task The project task for which you want to view commitment lines. If you want to see the commitment lines associated with all tasks, leave this box empty.
Include Non-Open Commitments A check box that you select to show all the commitment lines related to the project, including completed or canceled lines. If the check box is cleared, which is the default state, completed and canceled commitments aren't shown.
The table of the dialog box has the following columns.
Included An unlabeled check box that you select to add this commitment line to the change request if you then click Add Lines or Add Lines & Close.
PO Nbr.

The reference number of the purchase order.

PO Line Nbr.

The number of the commitment line.

Line Description

The description of the commitment line.

Order Qty.

The quantity of the commitment line.

This column is read-only. For a commitment line with the New Line or New Document status, this column is empty.

Line Amount

The amount of the commitment line.

Project Task

The project task associated with the commitment line.

Cost Code

The cost code associated with the commitment line.

This column is shown if the Cost Codes feature is enabled on the Enable/Disable Features (CS100000) form.

Inventory ID

The stock or non-stock item of the commitment line.

Vendor

The vendor associated with the commitment line.

PO Type

The type of the commitment, which can be one of the following: Normal Purchase Order or Project Drop-Ship.

Order Date

The date of the commitment.

Currency

The currency of the commitment line.

UOM

The unit of measure of the commitment line.

Unit Cost

The price of the specified unit of the commitment line in the currency of the commitment.

Qty. on Receipts

The received quantity of the commitment line.

Canceled

A check box that indicates (if selected) that the status of the document line related to the commitment is Canceled.

Completed

A check box that indicates (if selected) that the status of the document line related to the commitment is Completed.

Alternate ID The alternate identifier used for the item-subitem pair of the commitment line.
Attention: This column is hidden by default. You can display this column in the table by using the Column Configuration dialog box. For details, see Adjustment of the Acumatica ERP UI: To Personalize a View of a Form.
Promised The date when the item's delivery was promised.
Attention: This column is hidden by default. You can display this column in the table by using the Column Configuration dialog box. For details, see Adjustment of the Acumatica ERP UI: To Personalize a View of a Form.
Vendor Ref. The vendor reference number specified for the commitment.
Attention: This column is hidden by default. You can display this column in the table by using the Column Configuration dialog box. For details, see Adjustment of the Acumatica ERP UI: To Personalize a View of a Form.
 
Add Lines

Adds the selected lines to the change request. The dialog box remains open.

Add Lines & Close

Adds the selected lines to the change request and closes the dialog box.

Close

Cancels your selections and closes the dialog box.

Taxes Tab

The table on this tab contains information about the taxes to be paid on the change request. The tax details are calculated based on the tax categories:

  • On the Estimation tab for the revenue portion of the estimation lines
  • On the Markups tab for the markup lines

If integration with an external tax provider is configured and the provider's tax zone is selected in the change request, the taxes calculated by that provider are applied to the change request.

For built-in tax calculation, you can add or delete tax lines and adjust the taxable and tax amounts if the change request has the On Hold or Open status.

The table toolbar has only standard buttons.

Column Description
Tax ID

The identifier of the tax applied to the change request. For built-in tax calculation, you can select a tax that applies to at least one estimation or markup line based on the tax category of the line.

Tax Rate

Read-only. The rate of the tax. The rate is copied from the tax specified on the Taxes (TX205000) form.

Taxable Amount

The total amount of the revenue portion of the estimation lines and the markup lines that is subject to the tax. This amount is calculated based on the Tax Calculation Mode and the calculation rule of the tax.

For built-in tax calculation, you can override the calculated amount.

Tax Amount

The amount calculated for the tax based on the taxable amount, tax rate, and calculation rule.

For built-in tax calculation, you can override the calculated amount.

Table 5. Tax Info Section.

This section contains information about the tax settings used for the change request.

Element Description
Tax Zone

The tax zone of the customer.

The system inserts the tax zone based on the following priority:

  1. The Revenue Tax Zone specified for the project on the Addresses tab of the Projects (PM301000) form, if the Calculate Project-Specific Taxes check box is selected on the Projects Preferences (PM101000) form
  2. The tax zone associated with the address of the change request based on the mappings on the Ship-to Addresses tab of the Tax Zones (TX206000) form
  3. The tax zone of the customer
  4. The tax zone of the branch specified for the project

If no tax zone is found, this box is empty. You can override the inserted value. When you change the tax zone, taxes are recalculated.

Tax Calculation Mode

The mode that determines whether the amounts in the change request include tax. You can select one of the following options:

  • Tax Settings: The calculation rules specified for the taxes are used for built-in tax calculation. For external tax calculation, the settings of the tax provider are used.
  • Net: The amounts are treated as exclusive of tax.
  • Gross: The amounts are treated as inclusive of tax.

By default, the value is selected based on the following priority:

  1. The tax calculation mode of the customer's default location
  2. The default tax calculation mode of the external tax provider selected on the Tax Providers (TX102000) form
  3. Tax Settings

Taxes are recalculated when you change this value.

This box appears if the Net/Gross Entry Mode feature is enabled on the Enable/Disable Features (CS100000) form.

Tax Exemption Number

The exemption certificate number of the selected customer, which is used if your system is integrated with an external tax provider. By default, the value is pulled from the customer's location, but you can override it at the document level, if needed. The box appears if the External Tax Calculation Integration feature has been enabled on the Enable/Disable Features (CS100000) form.

By default, the value is copied from the tax settings of the customer's default location. You can override the inserted value.

This box appears if the External Tax Calculation Integration feature is enabled on the Enable/Disable Features (CS100000) form.

Tax Exemption Type

The tax exemption type of the customer's default location used for external tax calculation.

By default, the value is copied from the tax settings of the customer's default location. If no tax exemption type is specified for the location, this box is empty. You can override the inserted value.

This box appears if the External Tax Calculation Integration feature is enabled on the Enable/Disable Features (CS100000) form.

Address Tab

This tab displays the customer's address and contact information for the current change request.

Table 6. Contact Section. The information in this section is copied from the Bill-To Contact section of the Addresses tab on the Projects (PM301000) form for the associated project. If the change request has the On Hold or Open status, you can edit this information if you select the Override Contact check box.
Element Description
Override Contact

A check box that indicates (if selected) that the contact information can be overridden.

Account Name

The name of the customer.

Attention

The department or person to be noted on the attention line, if this line is used by your company.

Email

The email address of the customer's contact person.

Business 1

The phone number of the customer's contact person.

Business 2

The additional phone number of the customer's contact person.

Table 7. Address Section. The information in this section is copied from the Project Address section of the Addresses tab on the Projects (PM301000) form for the associated project. If the change request has the On Hold or Open status, you can edit this information if you select the Override Address check box.
Element Description
Override Address

A check box that indicates (if selected) that the address can be overridden for the current change request.

Address Lookup

Opens the Address Lookup dialog box.

This button is displayed on the form if the Address Lookup Integration feature is enabled on the Enable/Disable Features (CS100000) form and integration with web map services has been set up, as described in Integrating Acumatica ERP with Web Map Services. If the integration isn’t set up, the View on Map button is displayed instead.

Address Line 1

The first line of the project address.

Address Line 2

The second line of the project address.

City

The city of the project address.

Country

The country of the project address.

State

The state or province of the project address.

Postal Code

The postal code of the project address. An input mask for the postal code can be specified on the Countries/States (CS204000) form.

Latitude

The latitude of the project address, which can be used for tax calculation.

Longitude

The longitude of the project address, which can be used for tax calculation.

Validated

A check box that indicates (if selected) that the project address has been validated through integration with an address validation service. You can initiate address validation by clicking Validate Address on the More menu.

This check box is shown if the Address Validation Integration feature is enabled on the Enable/Disable Features (CS100000) form.

Detailed Description Tab

On the Detailed Description tab, you can view, add, change, or delete a detailed description of the change request.

The tab contains a rich text editor, which includes a text area and a formatting toolbar.

Markups Tab

On the Markups tab, you can view, add, change, or delete the document-level markups of the change request. When a new change request is created for a project, the default markups are copied from the Document Markups table on the Defaults tab of the Projects (PM301000) form and can be manually overridden.

A document-level markup is applied to the change request only if each part of the project budget key—project task, account group, and optionally, inventory item or cost code—are specified for the markup on this tab.

The table toolbar has only standard buttons.

Table 8. Table Columns
Column Description
Type The type of the document markup. You can select one of the following options:
  • %: A percentage markup that is applied to the sum of the line amounts of the estimation lines of the change request.

    You can define as many markups of this type as necessary. The markup subtotal is calculated as the sum of all these markup amounts.

  • Flat Fee: A markup whose amount is specified manually to be added to the total markup.
  • Cumulative (%): A percentage markup that is applied to all the previously applied percentage markups.
Description The brief description of the markup.
Value The percentage or amount of the markup, depending on the markup type.
Amount Subject to Markup

The amount to which the markup is applied.

For percentage and fixed markups, this amount is calculated based on the Line Amount values in the estimation lines of the change request on the Estimation tab, reduced by any inclusive tax amounts. For more information, see Change Requests: Configuration of Markups.

Markup Amount The calculated markup amount. The system calculates the markup amount depending on the type of the markup, the amount subject to markup, and the amount in the Value column as follows:
  • For the percentage markup type (%), the markup amount is calculated as follows: Markup Amount = Amount Subject to Markup * Value / 100, where the amount subject to markup is the sum of the line amounts of the estimation lines.
  • For the flat fee markup type (Flat Fee), the markup amount is specified manually in the Value column.
  • For the cumulative markup type, Cumulative (%), the markup amount is calculated as follows: Markup Amount = Amount Subject to Markup * Value / 100, where the amount subject to markup is the sum of all the previously applied percentage markups.
Project Task The project task that is associated with the markup.
Account Group The account group that is associated with the markup.
Cost Code

The cost code that is associated with the markup.

The column is shown if the Cost Code feature is enabled on the Enable/Disable Features (CS100000) form and Task and Cost Code is selected as the Revenue Budget Level for the project on the Summary tab of the Projects (PM301000) form.

Inventory ID

The inventory item that is associated with the markup.

The column is shown if Task and Item is selected as the Revenue Budget Level for the project on the Summary tab of the Projects (PM301000) form.

Tax Category

The tax category applied to the markup amount of the line.

When you add a line, the system inserts the tax category based on the following priority:

  1. The tax category of the selected inventory item
  2. The tax category of the selected project task

If neither the inventory item nor the project task has a tax category, this column is empty. You can select a tax category manually.

Approvals Tab

This tab displays the approval details for the selected change request. If change request approval has been configured, the change request is automatically assigned for approval when it is taken off hold. Authorized users can approve or reject the change request on the current form by using the Approve or Reject command, respectively. Alternatively, they can mass-process records that are pending approval by using the Approvals (EP503010) form.

This tab displays the approval entries associated with the selected record. If the record has existing Approved or Rejected entries and is put on hold for editing, these entries are preserved on the tab and the Obsolete check box is selected for them. Approval entries with a Pending decision are deleted. When the record is resubmitted for approval, new approval entries are created for this approval cycle. You can filter the approval entries on the tab by selecting one of the following filters: All Records, Approved, Current (default), Pending, or Rejected.

This tab is available only if the Approval Workflow feature is enabled on the Enable/Disable Features (CS100000) form and an approval map is specified for change requests in the Change Request Approval Map box on the Approval tab of the Projects Preferences (PJ101000) form. If no map is specified in this box, change requests do not require approval.

The table toolbar has only standard buttons.

Column Description
Assignee The identifier of the employee who’s assigned to approve the record.
Assignee Name The name of the employee who’s assigned to approve the record.
Workgroup The workgroup of the employee who’s assigned to approve the record.
Reviewer The identifier of the employee who actually reviewed the record.
Reviewer Name The name of the employee who actually reviewed the record.
Date The review date.
Decision The approval decision made for the record, which can be Pending, Approved, or Rejected, depending on the approval action performed.
Reason The reason the record has been approved or rejected (if applicable).
Obsolete

A check box that indicates (if selected) that the approval decision belongs to a previous approval cycle. The check box is selected for all Approved and Rejected approval entries when the record is put on hold for editing.

Side Panel

By using the side panel, you can view the change request that you have opened on the form while simultaneously viewing information related to the change request.

The side panel has multiple tabs, each of which you can view by clicking the tab's icon. These tabs are described below.

These tabs are displayed only when the Construction Project Management feature is enabled on the Enable/Disable Features (CS100000) form.

Tab Description
Drawing Logs

The Drawing Logs (PJ403000) form, which displays the list of the drawing logs for the change request selected on the current form.

Project Issues

The Project Issues (PJ3020PL) list of records, which displays the list of the project issues for the change request selected on the current form.

Requests for Information